Building construction - week 47
February 3, 2012 - Construction has passed the 70% completion mark.
Posted in: Development
February 3, 2012 - Construction has passed the 70% completion mark.
Posted in: Development
January 26, 2012 - Window frames and glass at the residential condos are 75% complete.
Posted in: Development
January 20, 2012 - The signature, convex facade of the building is prepared for the installation of window frames and glass.
Posted in: Development
January 13, 2012 - The building's permanent electrical service has been turned on. With accommodating temperatures most of the week, we enjoy good progress at the site.
Posted in: Development
January 6, 2012 - Work is proceeding well. Window glass is up to the 4th floor and residential balconies are prepped for concrete toppings.
Posted in: Development
December 30, 2011 - The first panes of glass were inserted this week.
Posted in: Development
December 22, 2011 - From everyone at the 1500 Project team, we wish you a happy holidays!
Posted in: Development
December 14, 2011 - The exterior cladding of the building, a premium Dryvit, began installation this week.
Posted in: Development
December 9, 2011 - Construction of the building passed a milestone this week. We are 2/3rds of the way to completion.
Posted in: Development
December 1, 2011 - The installation of the roofing system at the roof garden level has begun this week.
Posted in: Development